GT Control SW – TKS CSA – Rio de Janeiro, Brazil (GT11N2 LBTU, Alstom)

Wednesday, July 31, 2013 @ 06:07 AM
Project Name: TKS-CSA in Rio de Janeiro, Brazil
Client: Alstom Power Ltd. (Switzerland)
Scope: Process control system engineering, commissioning and support until commercial operation (Advant)
Start / Duration:

x

January 2008 / 20 months

The plant consists of two gas turbines of type GT11N2-LBTU installed in two separate shaft trains. Each shaft train consist of: GT, high pressure fuel gas compressor, low pressure fuel gas compressor and one generator. Each GT is followed by a diverter dumper, a by-pass stack and a heat recovery steam generator (HRSG).

The GT main fuel is a blast furnace gas produced in the blast furnace of the steel production process in an adjacent steel mill.

The power plant also includes a steam turbine which receives both the steam produced by the two HRSG (downstream the gas turbine) and the steam produced by the cocking plant in the steel mill.